Monitoring Changes in Delivery Schedules 
Use
When you manually create a new delivery schedule or automatically generate one from Electronic Data Interchange (EDI), the system checks the new delivery schedule against the old delivery schedules to ensure that tolerance levels are respected. If the system determines a problem, it issues a message and sets a delivery block.
Features
The system monitors changes of quantity in schedule lines with regard to specified tolerance levels. It checks:

A new JIT delivery schedule is checked against the current forecast delivery schedule and not against the old JIT delivery schedule. This is because JIT delivery schedules should follow the forecast delivery schedule as closely as possible.
A schedule line is valid when any of the following apply:
If any one of the three checks is successful, the check is considered as a whole successful. The system does not carry out any further checks.
Example
The following example of a new forecast delivery schedule shows how the system carries out these checks:
Tolerance quantity = 90
Tolerance days = 3
Schedule lines |
Old cumulative rel. qty. |
New cumulative rel. qty. |
05/07 |
1000 |
1100 |
05/08 |
1500 |
1600 |
05/09 |
2000 |
2000 |
05/10 |
2200 |
2100 |
05/11 |
2500 |
2400 |
05/12 |
3000 |
3000 |
The quantity is increased on 05/07. Because the deviation (100) exceeds the tolerance quantity (90), the new forecast delivery schedule does not pass the check against tolerance quantity. For this reason, the system also checks the deviation against tolerance days. It determines that the cumulative released quantity in the new forecast delivery schedule (1100) is less than the cumulative released quantity in the forecast delivery schedule from 05/10 (05/07 plus three tolerance days - 2200).The deviation on 05/07 is therefore permitted.
On 05/11, the system determines a decrease in quantity. Because the deviation (100) exceeds the tolerance quantity (90), the new forecast delivery schedule does not pass the check against tolerance quantity. For this reason, the system also checks the deviation against tolerance days. It determines that the cumulative quantity in the new forecast delivery schedule (2400) is greater than the cumulative released quantity in the old forecast delivery schedule on 05/08 (05/11 minus three tolerance days -1500). The deviation on 05/11 is therefore permitted.
Activities
To enter or view tolerance levels in quantity, percent, or number of days, mark an item in the delivery schedule and choose Goto ® Item
® More ® Delivery schedule control.