Repetitive Manufacturing: Planning

Description

The following functions are new to the planning area:

It is possible to access the planning table via a group of production lines (production line set). A work center hierarchy and a node work center within the hierarchy serves as selection criteria for these production line sets. The hierarchy is then exploded to the next level from the node work center. This means that, even if you only enter the hierarchy as selection criteria, only the work centers from the next lower level are displayed. The system displays the demand, the supply and the capacity load as a percentage.
It makes sense to include work centers in the hierarchy that are also defined as production lines in the production version. Here, you can branch into the individual production lines to change the run scheule quantities. The capacity requirements are automatically adjusted.
You can increase or decrease the number of periods (columns) by using the mouse to drag the window.
It is possible to branch into the capacity planning table for sequence planning from the planning table.
It is now also possible to carry out capacity leveling for the material as well as for the production line. The planning table is split into two for this purpose. Capacity requirements, supply and the load as a percentage are displayed in the upper half of the screen.
For more information on this subject, please refer to the release information "Capacity Planning: New and Changed Functions".

Change system parameters in customizing

Dispatching production quantities according to order dates or production dates