Processing a Single-Level WBS BOM 

Use

You change a WBS BOM with this function.

Prerequisites

You have fixed a material BOM or created a WBS BOM manually.

The same prerequisites apply here as for the processing of material BOMs. For more information, see the component BOM under Before making a change.

Features

If you create project-specific components in a WBS BOM, you work as you would for processing a material BOM.

You can enhance a WBS BOM by transferring items from an existing WBS BOM or from a material BOM.

Several people can simultaneously process different assemblies of a multi-level BOM. However, a specific assembly can only be processed by one person at a particular time. Therefore, this assembly is locked to other people until it is saved.

The following restrictions apply for WBS BOMs:

After processing a WBS BOM, select , so that the system can update the current components of a WBS BOM.

Activities

In the context menu of the BOM header, select the command Change or Change with change number.