Run Schedule Headers in Cost Object Controlling
Definition
Specification of the production version for a plant material and a validity period during which costs are collected.

From Release 4.6A onwards, you no longer create run schedule headers in repetitive manufacturing. Instead, you manufacture on the basis of production versions. Run schedule headers are only used if they were created in releases before 4.6A and therefore still exist in the system.
Structure
Depending on how the costs are settled, run schedule headers can be subdivided into run schedule headers with run schedule quantities and run schedule headers with partial orders.
For a run schedule header with run schedule quantities, production is split into production quantities by specifying quantities and periods. The costs of the run schedule header are collected on a Controlling object (product cost collector).
In the case of a run schedule header with partial orders, the production process uses the planned orders and production orders or process orders. The costs incurred in production are settled to these orders.
Integration
Run Schedule Headers in Cost Object Controlling
You collect the costs for run schedule headers on product cost collectors. You create these product cost collector manually. When you create a run schedule header for a production version, the system establishes a direct link to the product cost collector with the same characteristic value (material / plant / production version). The number of the product cost collector is specified in the run schedule header.
You perform logistical functions such as confirmations and goods issues for the run schedule header. The costs are collected on the product cost collector.

If you are manufacturing on the basis of sales orders and want to withdraw materials manufactured using run schedule headers as individual requirements materials, you do this by means of a planned order.
Reorganization of Run Schedule Headers
You should only reorganize a run schedule header if you are sure that no change in work in process or scrap can occur on the basis of that run schedule header, and that therefore no more work in process or scrap will need to be calculated for that run schedule header. Requirements:
It is useless to calculate work in process after final delivery, because the work in process is canceled at that point.
Once the accounting period is closed, it is not possible to make any further correction postings in Financial Accounting.
General Information on Run Schedule Headers
The repetitive manufacturing process delivers the semifinished and finished products to the warehouse stock. In contrast to order-related production, the planned orders from requirements planning are not converted into orders using the original lot size. Instead, multiple planned requirements are grouped into run schedule headers.
Run schedule headers are therefore not based on the lot size but on a period of time defined by the user. In some circumstances this period of time can be the entire life of the product. Cost Object Controlling is period-based, and measures the target costs and actual costs for the period for each product cost collector.
The costs are updated on a product cost collector that you first create manually in the menu of Product Cost by Period.
The run schedule header determines the following:
See also:
Recommendations and Notes for Repetitive Manufacturing Environments
Cost Object Controlling: Sales-Order-Related Production
Selected Logistical Processes and Cost Objects