Use
Progress analysis is the tool you use to determine planned and actual project progress values, and to compare the two sets of data. The system uses the overall planned costs to evaluate the work done, meaning that that evaluation is not dependent on the costs planned or posted by period. You can determine the relevant values at any time or as part of the period-end closing work that you plan in the
Schedule Manager. You can evaluate progress analysis data using the standard reports provided for this purpose in the project information system. You also have the option of defining your own reports, which you can tailor precisely to your information needs.
See
Evaluating Project Progress .Progress analysis is best used on projects where:
You can implement progress analysis as follows:

For example, capacity bottlenecks mean that your project is not keeping to schedule. However, costs are lower than expected. If it is now more important to keep to schedule than to keep to budget, the project management can enlarge the project team, which can then catch up.

If billing in your project takes place when a milestone is reached, progress analysis supports acceptance of the milestones. The data from the analysis documents the fact that the project team has achieved the milestone as agreed.

You can use progress analysis as an objective measuring instrument, comparing the success of several projects.
Features
As your project progresses, you can use progress analysis to obtain answers to the following questions:
Question |
Answered by |
Description |
How far should my project progress by a particular point in time? |
Planned POC |
The planned POC is the value of the work planned for up to a certain point in time, expressed as a percentage of all the work required. It is calculated using rules and based on the project data. |
What is the value of the planned services? |
BCWS |
This is the value of the planned services, relating to a reference factor (planned costs or overall budget) for the overall value of the work to be done. It is calculated as follows: BCWS = Planned POC * overall costs |
How far has my project actually progressed? |
Actual percentage of completion (POC) |
The POC is the value of the work actually done up to a certain point in time, expressed as a percentage of all the work required. It is calculated using rules and based on the project data. |
What is the value of the actual work performed? |
BCWP |
This is the value of the services actually rendered in relation to a reference factor (planned costs or overall budget) for the overall value of the services. It is calculated as follows: BCWP = Actual POC * overall costs |
What are the planned costs? |
Accumulated planned costs or overall budget |
The total value of the work to be carried out. |
Which values act as the reference factor for the overall value of the work done? |
Accumulated planned costs or overall budget |
The total value of the work to be carried out. |
What costs have already been incurred for the project? |
Actual costs, or ACWP |
Costs actually incurred. |
Are schedule variances occurring? |
SV = BCWP - BCWS |
Schedule variance (SV) |
What are the costs resulting from schedule variances? |
CV = BCWP - ACWP |
Cost Variance (CV) |
How accurate was my planning? What are the rates for cost overrun/underrun? |
CPI = BCWP /ACWP |
Value index (CPI) showing the ratio of the increase in value to the actual costs. |
What are the total costs to be expected if the cost variance continues? |
EAC |
Estimated costs at completion (EAC) resulting from the changed project processing? EAC is calculated as follows: EAC = (BCWS - BCWP) / CPI |