Carrying Out the Activity Backflush 

Use

If more (or less) activities are used to produce a material than you posted, you can use this function to repost the excess (or reduced) activities.

It may be necessary to do this if a difference exists after backflushing the planned and actual activities. These differences have to be balanced.

Procedure

  1. Starting from the initial screen for backflushing, choose Activity backflush.
  2. The system displays the screen for backflushing activities.

  3. Enter the appropriate plant and the assembly for which you want to backflush activities. If necessary, restrict your selection further.
  4. In the Reference quantity field , enter "0".
  5. This allows you to differentiate between posting a balance and posting a complete activity. When posting the complete activity, enter the appropriate reference quantity here.

  6. Choose Continue.
  7. The system proposes the operations, for which you can post a balance.

  8. Select the appropriate operations and confirm with Enter.
  9. Now enter the excess or reduced activities and save.