Dispatching, Deallocating and Rescheduling Manually 
Dispatching planned orders
Here, planned orders are dispatched to a sequence within the operating time.
The following planned orders are displayed in the section of the screen entitled Orders not yet dispatched and can be dispatched:
Planning Period as it has already planned the complete operating time of the planning period.

The system also schedules the planned orders that have not yet been dispatched and sets their start dates to the beginning of the first shift of the planning period. The operating time load cannot exceed 100 %.
To dispatch a planned order, proceed as follows:
If you use the automatic dispatching period, place the planned order in the desired planning period using the ‘drag and drop’ technique. The system then dispatches the order in the correct sequence (using the sales order number or item, for example).

You can also use guide lines as an extra aid when dispatching planned orders. If you use guides, you can dispatch planned orders with more precision.
To set the guides, choose Setting
If you select the start date with line, the system displays the guide at the start date of the order - at the left edge of the order symbol.
If you select the end date with line, the system displays the guide at the end date of the order - at the right edge of the order symbol.
Deallocating planned orders
You can deallocate planned orders that have already been dispatched. To do this, proceed as follows:
As an alternative to this procedure, you can also deallocate the selected planned order by choosing Deallocate. Then the system also moves the selected planned order to the section of the screen entitled Orders not yet dispatched - to the last day of the dispatching period.

If you have defined night shifts, the system moves the planned order to the first day of the following planning period.
Rescheduling planned orders
You can reschedule already dispatched planned orders.
The system displays the dialog box Reschedule.
As an alternative to this procedure, you can also place the planned order to the new dispatching period using the ‘drag and drop’ procedure.
The system dispatches the planned order in the newly selected dispatching period on the basis of the predefined planning procedure.
Rescheduling planned orders to another production line
To be able to dispatch planned orders to another production line, the following prerequisites must be fulfilled:
You can also dispatch the planned orders to another line in the desired planning period using drag & drop.