Displaying Pegged Requirements 

In the planning table, you can display the pegged requirements of a production quantity.

Procedure

  1. Double-click the production quantity.
  2. If the production quantity only consists of one planned order, a dialog box appears displaying the detailed data for this order.

    If the production quantity consists of several planned orders, the system first displays a dialog box listing all the planned orders that exist in this period. Double-click the planned order for which you want to see the pegged requirements. A dialog box appears displaying the detailed data for this order.

  3. Choose Pegged requirements.

The system branches to the Pegged Requirements screen where you can see all the pegged requirements.