Transferring Smoothed Requirements 
In the planning table, you can total demand (requirements) from sales orders and planned independent requirements and then distribute it equally over the individual periods as supply quantities. The system then distributes these quantities between the individual production versions.
Procedure
A dialog box Selection Days appears where you can define the period.
The system displays the dialog box Distribute Prod.Quantities
If no quota arrangement has been maintained for the material, check the proposed production versions in the dialog box and enter a quota of 1 if you want to produce the complete quantity (100%) on one production line.
Enter the appropriate quotas if you want to distribute the production quantity over several lines.
You return to the planning table.

As an alternative to this procedure, you can also use the Select buttons to select your period.
Result
The requirements were transferred as receipts and distributed to the appropriate production lines.