Increasing/Reducing Production Quantities Over a Period of Time 
Use
In the REM planning table, you can increase or reduce the production quantities over a certain period of time. Production quantities that have already been assigned to production versions are automatically adjusted according to the changes.
Procedure
You have the following options for increasing or reducing the quantities in the planning table:
The simplest option (using the select options):
The system reduces/increases the production quantities according to your selections.
Further options:
A dialog box Selection Days appears where you can define the period.
The system displays the dialog box entitled Increase/Decrease Quantities.
Alternatively, you can also proceed as follows:
The selected quantity is highlighted.
The system displays the dialog box entitled Increase/Decrease Quantities.
In both cases, proceed as follows:
The system reduces/increases the production quantities according to your selections.