Parameters for Detailed Scheduling

In Customizing for capacity planning you can specify parameters to be used in the orders of the various applications in detailed scheduling. You can define parameters for detailed scheduling for the following applications or objects.

The settings for detailed scheduling are only taken into account for planned orders and orders in Sales and Operations Planning SOP in the following case: if, when defining the scheduling levels, you have set the indicator specifying that detailed scheduling is to be carried out.

Which parameters can be maintained depends on the application. In what follows some parameters are described in more detail.

Scheduling can be carried out as backward scheduling, forward scheduling or scheduling to current date. You can also specify that only capacity requirements should be written. In lead time scheduling, the system switches to forward scheduling if an order start date is calculated that lies in the past. In the field Past start you can specify the number of days that the start date may be in the past, before the system switches to forward scheduling.

You can find more details on scheduling and scheduling parameters in the documents PP - Production orders, PM - Plant maintenance orders, PS - Project system, PP - Material Requirements Planning.