Scheduling Partially-Confirmed Operations 

There are two ways of scheduling partially confirmed operations:

The system calculates the remaining quantity for an operation according to the following formula:

Remaining quantity = original quantity - actual quantity

To calculate the duration of the operation segments, the remaining quantity and the forecast values or standard values must be entered into the formula if no forecast values were confirmed.

After the first partial completion confirmation, the duration for the setup is set to zero. The duration for teardown time is only set to zero at final confirmation.