Converting the Planned Order into a Production Order 

  1. Call up the transaction as follows:
  2. Menu Path

    From the MRP node, choose Evaluations ® Stock/Requirements List

    Transaction Code

    MD04

  3. Enter the following data:
  4. Field

    Data

    Material

    T-CV

    Plant

    1000

  5. Choose .
  6. Choose to display the details for your planned order.
  7. Choose -> Prod. Order (Convert planned order into production order).
  8. The Create Production Order: Header screen appears.

  9. Choose .
  10. You now see the operations.

    Make a note of the final operation in the list.

  11. Choose .
  12. To release the order, choose .
  13. To analyze the scheduling overview for the operations, choose Goto ® Graphic ® Gantt chart.
  14. Choose , then choose Yes.
  15. To display the current order status, choose.
  16. Choose .
  17. To schedule the order, choose .
  18. Choose .
  19. Write down the production order number displayed in the status bar.

  20. Choose .
  21. You see that the planned order has now been converted into a production order.

  22. Choose until the overview tree appears.