Scheduling Capacity Requirements 

  1. Call up the transaction as follows:
  2. Menu Path

    From the Production node, choose Capacity Planning ® Leveling ® Variable ® Online

    Transaction Code

    CM25

    The Profile dialog box appears.

  3. Enter the following data:
  4. Field

    Data

    Overall profile

    T-G001

  5. Choose .
  6. Enter the following data:
  7. Field

    Data

    Work center

    T-V

    Plant

    1000

    Capacity category

    002

  8. In the Capacity category line, choose .
  9. The Multiple Selection for Capacity Category screen appears.

  10. Choose the 1SingleVal tab.
  11. Enter the following data:
  12. Field

    Data

    Single value

    T-V

    T-E

    T-F

  13. Choose .
  14. To save the selection criteria as a variant, choose Goto ® Variant ® Save as variant on the Capacity Leveling screen.
  15. The ABAP: Save as Variant screen appears.

  16. Enter the following data:
  17. Field

    Data

    Variant name

    Variant T-V

    Description

    Variant for work center T-V

  18. Choose .
  19. To get the variant, choose .
  20. The ABAP: Variant Directory of Program RCCRY000 appears.

  21. Select the variant you have created.
  22. Choose .
  23. Choose .
  24. The Planning Table: T-G001 Dispatching with Production Versions screen appears.

  25. Choose Settings ® Scale ® Monthly period split to change the scale.
  26. Select the line with work center T-V in the top part of the screen.
  27. Choose Capacity.
  28. Enter the following data:
  29. Field

    Data

    In the Planning details section:

    Can be used by several operations

    Do not select

    By deselecting this indicator, you make sure that the system only processes one operation of this capacity category at a time. This means there is no multiple loading.

  30. Choose .
  31. To skip any warning or information messages, choose .

  32. Select a planned order in the bottom part of the planning table and dispatch it automatically by choosing .
  33. Repeat this step for all planned orders.
  34. If there is no more capacity at work center T-V, the operations are not dispatched any more.

  35. The planned orders are scheduled again, but not dispatched. They remain in the pool, and you can dispatch them at the new production line by selecting the planned orders and moving them to the work centers.
  36. Choose .

The overview tree appears.