Menu Path |
Logistics ® Production ® Production Planning ® Demand Management ® Planned Independent Requirements ® Create |
Transaction Code |
MD61 |
Field |
Data |
Material |
T-CV |
Plant |
1000 |
Version |
00 |
The Settings: Requirements Parameters dialog box appears.
Field |
Data |
Plant |
1000 |
Requirements type |
LSF |
Version |
00 |
Period ind. |
W |
Display |
Period split |
Active |
Select |
Item screen |
Select |
History indicator |
Select |
If there already is a requirement, the system issues a log. To confirm the information message, choose
.
The Create Planned Independent Requirements: Item Screen appears.
You must now specify the planned quantities for the next few weeks on the Create Planned Independent Requirements: Schedule Lines screen. You must plan 70 units for each week.
Fields |
Data |
Planned qty |
70 (for each week) |
To skip any information or warning messages, choose
.