Planning a Product 

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Production ® Production Planning ® Demand Management ® Planned Independent Requirements ® Create

    Transaction Code

    MD61

  3. Enter the following data:
  4. Field

    Data

    Material

    T-CV

    Plant

    1000

    Version

    00

  5. Choose Reqmts parameters.
  6. The Settings: Requirements Parameters dialog box appears.

  7. Enter the following data:
  8. Field

    Data

    Plant

    1000

    Requirements type

    LSF

    Version

    00

    Period ind.

    W

    Display

    Period split

    Active

    Select

    Item screen

    Select

    History indicator

    Select

  9. Choose .
  10. Choose to confirm the information message.
  11. Choose .
  12. If there already is a requirement, the system issues a log. To confirm the information message, choose .

    The Create Planned Independent Requirements: Item Screen appears.

  13. Choose the Table tab.
  14. Select the first item.
  15. To check the current warehouse stock, choose Environment ® Stock reqmts/list.
  16. Choose .
  17. You must now specify the planned quantities for the next few weeks on the Create Planned Independent Requirements: Schedule Lines screen. You must plan 70 units for each week.

  18. Enter the following data for the next eight weeks:
  19. Fields

    Data

    Planned qty

    70 (for each week)

  20. Choose .
  21. To skip any information or warning messages, choose .

  22. Choose .
  23. Choose .