Scheduling and Scheduling Results on the Screen 

This section describes how to call up the function Scheduling and how to display the scheduling results on the screen.

Calling up Scheduling

To call up scheduling, proceed as follows:

  1. Call up a process order (only in create or change mode).
  2. Select the menu options Process order ® Functions ® Schedule. The system schedules the process order and creates a scheduling log.

Scheduling Results

You can call up the scheduling log, proceed as follows:

Select Goto ® Logs ® For scheduling. The system displays an overview of the messages collected.

Date/Quantity Overview

Via the header screen Date/quantity overview, you can display the release, start and finish dates of the process orders as well as of the planned order, if you have converted a planned order.

Detail Screen of Operation Dates

To display the dates of the individual operations and phases, proceed as follows:

  1. In the Operation overview screen, flag the operation or phase whose dates you want to display.
  2. Select the menu options Operation ® Overview of dates. The system displays a detail screen showing the dates (and times) of the operations and phases you have selected.