Create Work Breakdown Structure 
Prerequisites
You have defined an investment project.
Procedure
Menu Path |
Accounting ® Investment Management ® Investment Projects ® Master Data ® Project Builder |
Transaction |
CJ20N |
Field |
Data |
Project definition |
Your number, for example I/2000 |
.Your project is added to the project definitions listed.
There is already a top WBS element. You now add further WBS elements.
Field |
Data |
WBS element (2nd field) |
Foundation |
Field |
Data |
WBS element (2nd field) |
Building shell Heating Interior |
Field |
Data |
WBS element (2nd field) |
Windows |
Field |
Data |
WBS element (2nd field) |
Doors |
Release the project so that planning can be entered for it.
Result
Your project is now structured. At the same time, the release of the project triggered the system to create assets under construction (AuCs). You can display the assets under construction for each WBS element. Choose Edit
® WBS element ® Investment programs ® Asset under construction.