Processing a Cost Estimate for an Appropriation Request 
Prerequisites
You are in the
Processing Appropriation Requests transaction.
The pushbutton for creating a cost estimate is only visible when certain conditions are fulfilled. For more information on these conditions, refer to
Procedure
The screen for Easy Cost Planning appears.
Using Easy Cost Planning.
You return to maintenance of plan values. The plan value table now contains the combined costs from the cost estimate. The system interprets the combined costs 100% as investment costs, and enters the values in the column for investment costs in the plan value table.

If you subsequently modify the cost estimate later, this percentage remains unchanged.

Choose