In release 3.0, not only can you use the fixed lot size with splitting and overlapping, but you can also apply this technique to the period lot size. In each period, the lot is split into partial quantities for which planned orders are created. The planned orders are dated so that they overlap each other.
The period lot size with splitting and overlapping represents a campaign based on periods. On the other hand, the fixed lot size with splitting and overlapping represents a campaign based on quantites.
Steps to take
In Customizing, you must enter the indicator for overlapping (backward or
forward) for the period lot-sizing procedure.
In the material master record, you must enter the cycle time. This is the time
that determines how the individual planned orders for the period lot are to
overlap each other.
The partial quantities into which the planned order is to be split, is set in
the field, maximum lot size (and not in the field, rounding value).
For the period lot size with splitting and overlapping, you must enter the
overlapping indicator for the period lot size that you want to use for this
technique.
Please read the corresponding chapter in the Implementation Guide.