Material Requirements Planning: New Functions in the
Availability Check
Description
1. The availability check can be carried
out at header level of the planned order from release 3.0. This means that, if
you create or change the planned order in the header screen, the system checks
at the same time for all components whether these parts are available for the
quantities required.
Steps to take
In the header data screen of the planned order,
select, Edit -> Mat.availability.
The system displays a list of the components with availability data and
various evaluation and display functions.
a) You can switch off the availability
check for a material. This is especially usefull for materials that are always
in plentiful supply, for example, screws. To exclude such materials from the
availability check, in the material master record, MRP 2 screen, set the
availability check field to No
check.