The following new functions are now available with release 3.0. You can:
A detailed description of the individual points is provided below:
In release 3.0, it is possible to access the capacity evaluation from the stock/requirements list. However, no changes can be made from here - the display is for information purposes only.
It is now possible to use the planning calendar periods to display capacity planning data.
In 3.0, it is possible to check and, if necessary, change several planned orders from the material view. Changes to capacity can be viewed immediately.
In contrast to the functionality of release 2.2, in 3.0 work centers and capacity are no longer separate, but are jointly provided for selection in one pushbutton. You now select a resource, that is, you select the available capacity for a work center.
A function is available which can be used to check which work centers are already overloaded. Moreover, you can determine the following in a special dialog box:
In 3.0, it is possible to branch from the planning result of the interactive planning and from the stock/requirements list into the graphics planning table. Here, the following processing options are available:
Please refer to the online documentation capacity planning for more detailed information on the new functions in capacity planning.