The assigned value for projects is calculated from:
Actual costs on the budget carrying WBS element
Statistical actual costs on the budget carrying WBS element
Actual costs from lower-level WBS elements, if these do not have any budget
Statistical actual costs from lower-level WBS elements, if these do not have any budget
Commitments on the budget carrying WBS element
Commitments from lower-level WBS elements, if these do not have any budget.
Maximum from plan and actual costs + commitments from assigned networks or orders. For more information, see the implementation guide (IMG) under Project System Õ
Costs Õ
Plan Costs Õ
Credit by settlement to a budget controlled object (such as an internal order, or WBS element)
The following is not relevant for calculation of the assigned value:
Actual costs with a cost element that was defined in Customizing for availability control as an exempt cost element. For more information, see the implementation guide (IMG) under Project System ®
Cost ®Budget ®
Actual costs that were incurred by a business transaction that does not belong to the valid
transaction groups in availability control. This situation cannot occur if you did not
++
maintain the
tolerance limits as a transaction group in Customizing. For more information, see the implementation guide (IMG) under Project System ®
Costs ®
Budget ®Specify Tolerance Limits.
Credits by settlement to an object that is not budget controlled (such as a cost center)