Procedure: Cross-System Planning Situation 

Purpose

This process describes how you evaluate the MRP run for a material that is maintained in several systems, which means cross-group.

Prerequisites

Customizing

Process flow

  1. When you start the evaluation, the system uses the customer distribution model to check which plants are in which logical SAP System.
  2. The system checks in each plant whether the material involved exists. When this is the case, the MRP data required is requested by means of synchronized Remote Function Calls (RFCs).
  3. If the system that is calling cannot access the required information (when no access authorization exists, for example), it logs an error, which you can display.
  4. The planning situation is displayed on the screen. The report contains all MRP elements that are defined in the specified evaluation layout, for example production orders, purchase orders, sales orders, reservations, and warehouse stocks.