Master Production Scheduling: Comparison of Planning
Result and Planning Situation
Description
The planning result displays the result of the last planning run (as in the
MRP list). The planning situation takes all changes in stock, receipts and
issues that occur between planning runs into account (as in the
stock/requirements list). It is possible to compare these two evaluations with
each other. In so doing, you receive a display of the changes that have
occurred since the last planning run.
You can only access the comparison from the initial screen of the
planning situation for a material:
Select the field, Compare with
planning result.
You branch into the "Operative Planning Situation - Operative Planning
Result". The system highlights the operative planning result.
- If you only want to display the planning situation, select,
Edit -> Only original.
- If you only want to display the planning result, select,
Edit -> Only compare values.
- To display both the planning situation and the planning result, select,
Edit -> Original and compar. .
- To check the differences between the planning situation and the
planningresult, select,
Edit -> Differences.
When accessing more or less line details for the
elements, the data is always accessed for the planning situation and for the
planning result.