Master Production Scheduling: Comparison of Planning Result and Planning Situation

Description

The planning result displays the result of the last planning run (as in the MRP list). The planning situation takes all changes in stock, receipts and issues that occur between planning runs into account (as in the stock/requirements list). It is possible to compare these two evaluations with each other. In so doing, you receive a display of the changes that have occurred since the last planning run.

You can only access the comparison from the initial screen of the planning situation for a material:

Select the field, Compare with planning result.
You branch into the "Operative Planning Situation - Operative Planning Result". The system highlights the operative planning result.
When accessing more or less line details for the elements, the data is always accessed for the planning situation and for the planning result.