Demand Management: Period of Adjustment for
Unconsumed Planned Independent Requirements
Description
Using the period of adjustment, a period can be specified in which planned
independent requirements are not included in the planning run. This means
that;
- no order proposals are created by the planning run for planned independent
requirements that lie within the period of adjustment
- no order proposals are created by the planning run for planned independent
requirements for which no firmed receipts or firmed order proposals have been
scheduled or which have moved into the period of adjustment
The period of adjustment is specified in the material master record in the
MRP 3 screen, in the field, ResHZ VPL.