Demand Management: Period of Adjustment for Unconsumed Planned Independent Requirements

Description

Using the period of adjustment, a period can be specified in which planned independent requirements are not included in the planning run. This means that;

The period of adjustment is specified in the material master record in the MRP 3 screen, in the field, ResHZ VPL.