Transferring the Flexible Planning Results 

Use

You can carry out flexible planning (sales and operations planning) for a material, which is planned with a production lot, and then transfer the planning results to Demand Management with reference to the appropriate production lot (WBS element).

Prerequisites

The prerequisites for transferring the results for each production lot from flexible planning to Demand Management are:

You have created an information structure which includes a characteristic with a data element or the domain PS_POSNR (WBS element).

In Customizing for Sales and Operations Planning, in the IMG activity "Set parameters for info structures and key figures", you have set the Transfer to Demand Mgmt with user exit indicator. You then choose the function key: Set parameters for info structures and key figures.

Features

In order to transfer the results, you have to use the following functional enhancements. These enhancements enable data from other levels other than material/plant to be transferred:

MCP20020 (both online and in batch)

MCP20021 (both online and in batch)

MCP20023 ( for batch)

 

If you transfer the data online, you have to enter the production lot number (WBS element) by choosing Extras -> WBS element.