BOM Transfer and Assemblies Used More than Once 
Use
Assemblies Used More than Once in Order BOMs
Before you trigger a BOM transfer to the Project System, ensure that all assemblies you transfer, can be uniquely identified. This guarantees that the system determines the quantities for all items correctly. This is only the case if no assembly in the multi-level BOM is used on more than one node.
Activities
Check in
order analysis, whether one or more assemblies are used several times in the multi-level BOM. The Edit Order BOM screen appears.
Order analysis. The List of Results for the Analysis screen appears..
The assemblies listed on this tab page are used more than once in the multi-level BOM for the sales order item.
If an assembly is used more than once, replace the material on the individual nodes, so no two BOM headers in the multi-level BOM have the same material number.
For configurable assemblies use
instantiation in variant configuration to do this. For non-configurable assemblies use
material replacement in the order browser.