Determination of Basic Load (Report RCCYLOAD) 

Use

When you use the capacity availability check for the first time or when you only use the availability check or the planning table irregularly for orders relevant to production, the basic load is not current; that is, it does not contain all the capacity requirements that are relevant to the capacity availability check. In this case, you should specify the basic load before the capacity availability check using the report RCCYLOAD.

Procedure

  1. Choose Tools ® ABAP Workbench ® Development ® ABAP Editor
  2. The ABAP Editor: Initial screen appears Einstieg.

  3. Enter RCCYLOAD as the program, and choose Program ® Execute ® Direct

You can call up the report for Determination of basic load in Plant Maintenance and in Customer Service by choosing:

The Initialization of Basic Load screen appears.

  1. Select the capacity requirements from the screen sections Order-related data and Operation and requirements-related data that you want to incorporate into or remove from the basic load.
  2. The selection criteria are linked by a logical AND.

  3. Set the following indicators in the screen section for operation and requirements-related data as required:
  4. If you want to:

    Set the indicator:

    Select all capacity requirements that load a pooled capacity and fulfill all the selection criteria other than the work center

    Take into account all capacity requirements for pooled capacities affected

    Select all capacity requirements for an order if at least one capacity requirement meets the selection criteria

    Always take whole orders into account for the basic load

     

  5. Choose in the Control screen section what the system should do:

If the system should:

Choose:

Display the number of selected capacity requirements

Determine number of capacity requirements affected

  • Incorporate the selected capacity requirements into the basic load and
  • Set the Capacity confirmed indicator for the corresponding operations

Take into account capacity requirements selected for the basic load

  • Remove the selected capacity requirements from the basic load and
  • Remove the Capacity confirmed indicator for the corresponding operations (if set)

Remove capacity requirements selected from the basic load

 

  1. Choose Program ® Execute.