As from Release 3.0, you can carry out mass changes for BOM components. The following objects can be replaced through mass change in bills of material provided certain requirements are met:

The material type, the base unit of measure, and the unit of issue must be identical for both the old and the new material.
Both documents must be of the same document type.
Both classes must be of the same class type.

In addition to the data identifying the old and the new object, you also can enter the following data on the initial screen:

The required quantity of the old BOM component is multiplied by this factor to calculate the required quantity of the new BOM component.
In the overview, you see only those bills of material whose data is identical with the selection criteria (plant, usage, laboratory/office).

When you have confirmed the selection criteria, the system checks in which BOM categories (such as material BOM, document structure) the object is used.
If the object is used in various BOM categories, you can choose the BOM categories you require on a separate screen.

If the selected bill of material is a multiple bill of material, the material is replaced in all alternatives.
The material is only replaced in the selected alternatives.
From the Edit menu, then choose function Replace.

The selected bills of material are automatically changed by the system. A log informs you of the activities the system has performed.