Backflushing for Scrap for Reporting Point 2 

Use

In a previous process step you confirmed that 130 units have reached the first reporting point. You now continue production. You have removed 10 units of R-1220 from the inventory and included them in the assembly, but only later discovered that this part is defective. The 10 assembly units concerned now have to be separated out as scrap. As part R-1220 is defective you are no longer going to use it in the production of your PC components. Instead you substitute R-1220 with C-1230, which is similar but a little more expensive.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Production ® Repetitive Manufacturing ® Backflush ® REM Backflush

    Transaction Code

    MFBF

  3. Choose Scrap, then enter the following data:
  4. Field

    Europe

    North America

    Assembly backflush

    Select

    Select

    Scrap quantity

    10

    10

    Reason

    0003

    0003

    Posting date

    Current date

    Current date

    Document date

    Current date

    Current date

  5. On the Make-to-stock tab page, enter the following data:
  6. Field

    Europe

    North America

    Material

    C-1113

    C-1113

    Plant

    1200

    3200

    Production version

    0001

    0001

    RP backflush

    Select

    Select

    Reporting point

    0030

    0030

  7. Choose Post with Correction.
  8. In the REM Backflush Transaction Variant: None screen check the appropriate component withdrawals for the scrap quantity. Enter 0001 as storage location.
  9. Choose Actual activities:
  10. In the Operation Selection for Backflushing Actual Activities select the operations and choose .
  11. Check the confirmation data and choose .
  12. Check the confirmation data for this operation as well, and choose .
  13. Choose until the overview tree appears.
  14. If the Exit Processing dialog box appears, choose Yes.