Target=Actual Activity Allocation 
Purpose
Target=actual activity allocation enables you to portray an activity network with more than one level and iteratively using the operating rate as a tracing factor. The actual activity quantities to be allocated are entered indirectly. To do this, the system uses the planned activity inputs from the receiver. The operating rates from the receiving cost centers are also used.
You can find more information about this process under
.
Process Flow
You can find the data for this process under
.