Use
Cost objects in different SAP applications are all settled using the same method. During settlement, the incurred actual costs for an object are either completely or partially settled to one or more receivers. On the receivers, you can use reporting to display this. The system creates the corresponding credit postings for the sender at the same time. You can still see the original debit on the sender.
In this example, costs were posted to an order and are now to be settled to two receivers, according to the source cost element used for posting them to the order. The receivers are a cost center and a fixed asset.
Procedure
Menu Path |
Accounting ® Controlling ® Internal Orders ® Period-End Closing ® Single Functions ® Settlement ® Individual Processing |
Transaction Code |
KO88 |
:Field |
Europe |
North America |
Controlling area |
1000 |
2000 |
Field |
Europe |
North America |
Order |
100099 |
100039 |
Settlement period |
001 |
001 |
Posting period |
001 |
001 |
Fiscal year |
Current year |
Current year |
Processing type |
Automatic |
Automatic |
Test run |
Selected |
Selected |
.The Basic list contains a message stating that processing was completed without errors.
.This shows the amounts that were settled to each receiver.
Sender.The system displays the cost elements and amounts that were debited to the settled order.. You can follow up the connection between the displayed amounts for each cost element, and the amounts settled (according to each source assignment) for each receiver.
.
Receiver.The settlement receiver and the credited values are displayed with the corresponding settlement cost elements.

Here you need to note the difference between the source structure and the allocation structure. The allocation structure determines the settlement cost elements used for settlement, independently of the source structure mentioned above.
until the overview tree appears.