Settling Orders 

Use

Cost objects in different SAP applications are all settled using the same method. During settlement, the incurred actual costs for an object are either completely or partially settled to one or more receivers. On the receivers, you can use reporting to display this. The system creates the corresponding credit postings for the sender at the same time. You can still see the original debit on the sender.

In this example, costs were posted to an order and are now to be settled to two receivers, according to the source cost element used for posting them to the order. The receivers are a cost center and a fixed asset.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Accounting ® Controlling ® Internal Orders ® Period-End Closing ® Single Functions ® Settlement ® Individual Processing

    Transaction Code

    KO88

  3. If the Set Controlling Area dialog box appears, enter the following data then choose :
  4. Field

    Europe

    North America

    Controlling area

    1000

    2000

  5. Enter the following data:
  6. Field

    Europe

    North America

    Order

    100099

    100039

    Settlement period

    001

    001

    Posting period

    001

    001

    Fiscal year

    Current year

    Current year

    Processing type

    Automatic

    Automatic

    Test run

    Selected

    Selected

  7. Choose .
  8. The Basic list contains a message stating that processing was completed without errors.

  9. To display the detail list, choose .
  10. This shows the amounts that were settled to each receiver.

  11. Select sender order 100099 (100039) and choose Sender.
  12. The system displays the cost elements and amounts that were debited to the settled order.. You can follow up the connection between the displayed amounts for each cost element, and the amounts settled (according to each source assignment) for each receiver.

  13. To return to the Detail list, choose .
  14. Choose Receiver.
  15. The settlement receiver and the credited values are displayed with the corresponding settlement cost elements.

    Here you need to note the difference between the source structure and the allocation structure. The allocation structure determines the settlement cost elements used for settlement, independently of the source structure mentioned above.

  16. Choose until the overview tree appears.