Settling Orders 

  1. Call up the transaction as follows:
  2. Menu Path

    Accounting ® Controlling ® Internal Orders ® Period-End Closing ® Single Functions ® Settlement ® Collective Processing

    Transaction Code

    KO8G

  3. Enter the following data:
  4. Field

    Europe

    North America

    Selection variant

    SAP_25

    SAP_25_CA2000

    Settlement period

    001

    001

    Posting period

    001

    001

    Fiscal year

    Current year

    Current year

    Asset value date

    No entry

    No entry

    Test run

    Selected

    Selected

    Detail list

    Selected

    Selected

  5. Choose .
  6. An overview appears, with a note that processing was completed with no errors and that five orders were settled.

  7. Choose .
  8. The detailed list shows the amount to be settled, sender and the receiver.

    If does not appear, actual settlement was already executed without setting the Test run indicator. If that is the case, choose , until the Actual Settlement: Orders screen appears. Choose Settlement ® Reverse, without setting the Test run indicator. Continue from step 2.

  9. Select sender order 800047 (800060) and choose Sender.
  10. The system displays the cost elements and amounts that were debited to the settled order.. The cost elements are primary cost elements.

  11. Choose .
  12. In the detailed list, select sender order 800045 (800058) and choose Sender.
  13. Choose Select.
  14. Double click on display variant /id_COOM60.
  15. You see that this order was debited with the costs from the settlement of orders 800047 (800060) and 800048 (800061) from the same settlement run.

  16. To go back to the detailed list, choose .
  17. Select sender order 800048 (800061) and choose Receiver.
  18. The settlement receiver and the settled amounts appear for each settlement cost element .

  19. Choose until the overview tree appears.