Use
The following steps explain the customizing settings, and are intended for display purposes. For this reason, you are requested not to change any data.
Procedure
Menu Path |
Tools ® AcceleratedSAP ® Customizing ® Edit Project |
Transaction Code |
SPRO |
Field |
Europe |
North America |
Controlling area |
1000 |
2000 |
You can see cost elements 400000 - 419000 have been specified as the base.
The Overhead type column contains the entry 1 for actual overheads and the entry 2 for planned overheads. A quantity-based overhead of USD 10 has been defined per piece for each row.
Field |
Europe |
North America |
Controlling area |
1000 |
2000 |
You can see that the overhead rate is allocated using cost element 655100I and is credited to cost center 4130. The * value in the Fixed % field shows that the costs credited to the credit object are distributed in the same way (by fixed and variable portions) as the overhead allocation on the debited object.