Defining Costing Sheets 

Use

The following steps explain the customizing settings, and are intended for display purposes. For this reason, you are requested not to change any data.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Tools ® AcceleratedSAP ® Customizing ® Edit Project

    Transaction Code

    SPRO

  3. Choose SAP Reference IMG.
  4. Choose Controlling ® Internal Orders ® Actual Postings ® Overhead Rates.
  5. Choose in front of Maintain Costing Sheets.
  6. Select the quantity-based overhead row in the CO01 costing sheet, and double-click in the dialog structure on Costing sheet rows.
  7. Select the row for the Base B300 entry, and double-click on Base.
  8. If the Set Controlling Area dialog box appears, enter the following data, and choose :
  9. Field

    Europe

    North America

    Controlling area

    1000

    2000

    You can see cost elements 400000 - 419000 have been specified as the base.

  10. Choose .
  11. Select the row for the Overhead O300 entry, and double-click on Overhead rate.
  12. The Overhead type column contains the entry 1 for actual overheads and the entry 2 for planned overheads. A quantity-based overhead of USD 10 has been defined per piece for each row.

  13. Choose .
  14. Select the row for the Credit C03 entry, and double-click on Credit.
  15. If the Set Controlling Area dialog box appears, enter the following data, and choose :
  16. Field

    Europe

    North America

    Controlling area

    1000

    2000

    You can see that the overhead rate is allocated using cost element 655100I and is credited to cost center 4130. The * value in the Fixed % field shows that the costs credited to the credit object are distributed in the same way (by fixed and variable portions) as the overhead allocation on the debited object.

  17. Choose until the overview tree appears.