Maintaining Tolerance Limits 

  1. Call up the transaction as follows:
  2. Menu Path

    Tools ® AcceleratedSAP ® Customizing ® Edit Project

    Transaction Code

    SPRO

  3. Choose SAP Reference IMG.
  4. Choose Controlling ® Internal Orders ® Budgeting and Availability Control
  5. Choose in front of Define Tolerance Limits for Availability Control.
  6. You can see that the tolerance limits are defined in relation to a particular budget profile in the % Usage (percentage usage) and Absolute variance columns. In this way, the tolerance limits are related to the budgeted orders of those order types that have been assigned this budget profile in Customizing.

    The overview screen displays the following for controlling areas 1000 (Germany) and 2000 (USA) (see first column) for budget profile 000001: an initial tolerance limit of 95% (budget usage of 95%) and a second tolerance limit of 105% (budget exceeded by 5%). This process relates to the second tolerance limit.

    To define a tolerance limit completely, you still have to specify which business transaction group is to be included in the control (Business transaction group column) and the actions that should take place if a limit is exceeded (Act. column).

  7. Select the business transaction group field in on of the rows of your controlling area and choose the F4 help.
  8. It displays the business transaction groups (for example, purchase order, goods issue, financial accounting document) that can be used for differentiating the availability control.

    ++ has been chosen for the example. This means that all business transaction groups in the availability control are included.

  9. Choose from the dialog box.
  10. Place your cursor under the Action field, in one of the rows of your controlling area and choose the F4 help.

This displays the following activities that are triggered if the tolerance limit is exceeded:

  1. Choose from the dialog box.
  2. Choose until the Customizing: Execute Project screen appears.