Changing Order Budget Values 

  1. Call up the transaction as follows:
  2. Menu Path

    Accounting ® Controlling ® Internal Orders ® Budgeting ® Original Budget ® Change

    Transaction Code

    KO22

  3. If the Set Controlling Area dialog box appears, enter the following data then choose :
  4. Field

    Europe

    North America

    Controlling area

    1000

    2000

  5. Enter the following data:
  6. Field

    Europe

    North America

    Order group

    DEV-BUDGET

    DEV-BUDGE2

    Order type

    0100

    0101

  7. Choose .
  8. The total budget values for the original budget for the time frame current year are displayed.

  9. Select the first order and choose Annual overview.
  10. The values displayed include the original budget, the current budget and the assigned funds for each time frame.

  11. To return to the budget display, choose Order overview in the annual overview.
  12. Select an order and a column, then choose Edit ® Copy view.
  13. The system displays a dialog box that you can use to copy the current view to the budget values. The values to be copied can also be changed by entering a percentage rate. You can also specify whether to overwrite the existing budget values or to add the copied values to the budget.

  14. Choose .
  15. Select the first order and choose Edit ® Revaluate.
  16. You can enter a revaluation percentage or an amount in the dialog box.

  17. Choose .
  18. Choose Extras ® Line items.
  19. The development of the budget with line items for the following categories is displayed: original budget, supplement and return.

    The total is the budget currently existing.

  20. Choose until the overview tree appears.