Copying Basis Plan Version for Cost Centers 

Use

In this process step, you copy the cost centers for basic plan version 20 into plan version 21. You use plan version 21 to perform the plan reconciliation. As you can repeat the copying process, you can also repeat the plan reconciliation.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Accounting ® Controlling ® Cost Center Accounting ® Planning ® Planning Aids

    Transaction Code

    KP97

  3. If the Set Controlling Area dialog box appears, enter the following data then choose :
  4. Field

    Europe

    North America

    Controlling area

    1000

    2000

  5. Enter the following data:
  6. Field

    Europe

    North America

    Target cost centers

       

    All cost centers

    Select

    Select

    Reference (plan)

       

    Version

    20

    20

    Period

    1

    1

    To

    12

    12

    Fiscal year

    1997

    1997

    Ref.CCtr=Tgt CCtr

    Select

    Select

    Target (plan)

       

    Version

    21

    21

    Period

    1

    1

    To

    12

    12

    Fiscal year

    1997

    1997

    Plan data

       

    All plan data

    Select

    Select

    Structure with values

    Select

    Select

    Processing options

       

    Reset and overwrite

    Select

    Select

    Background processing

    Deselect

    Deselect

    Test run

    Deselect

    Deselect

    Detail list

    Select

    Select

  7. Choose .
  8. In the dialog box, choose Yes.
  9. The system copies the plan data to version 21. Existing data are overwritten and the structure and values are copied. The system reset plan version 21 before copying, and then it copied all plan data from version 20.

  10. Choose until the overview tree appears.
  11. In the dialog box, choose Yes.