Additional Process Information 
Variance determination is an analysis tool that you can use to calculate the balance between target costs and the split actual costs on the activity types (input side). You can do the same between target costs and allocated actual costs (output side) in different variance categories. You can make this calculation according to cost element for each cost center or activity type, and find its cause.
Actual costs on the input side are costs that flow to the cost center (credits, excepting activity allocation are regarded as a reduction of these costs).
Actual costs on the output side are the credits caused by activity allocations. The variances are displayed on the input and output sides in different variance categories.
The variance categories on the input side are:
The variance categories on the output side are:
You can specify the determined variance categories in Customizing that you require. Variance categories that were deactivated are displayed on the input side in the input variance, and on the output side in the remaining variance.
Before the system can calculate the variances, the actual data must be assigned to the planning data and be split up into fixed and variable portions. This part is described as actual cost splitting, and is automatically part of the variance calculation. Once this has been completed, the system determines each variance category.