Displaying a Cycle for Indirect Activity Allocation 
Menu Path |
Tools ® AcceleratedSAP ® Customizing ® Edit Project |
Transaction Code |
KSC8 |
SAP Reference IMG.
Define Indirect Activity Allocation.
Choose.If the Set Controlling Area dialog box appears, enter the following data then choose
:
Field |
Europe |
North America |
Controlling area |
1000 |
2000 |
Field |
Europe |
North America |
Cycle |
I-IAP1 |
I-IAP3 |
Starting date |
01.01.1995 |
01.01.1995 |

This cycle is used only for company code 1000 Germany or 3000 U.S.A., as these are the only company codes in which indirect activity allocation occurs. Company codes 2000 Great Britain (or 4000 Canada) use assessment to allocate secondary costs.
.
.You see which areas are to be allocated using indirect activity allocation.
.You can see the specification of the sender and receiver cost centers for the allocation of cost center 1000 (Corporate Service). In this segment, the sender costs are allocated via activity type 1510 (caution, we use activity type categories 2 and 3).
The system displays the drilldown for the receiver cost center set. This contains all cost centers from numbers 1110 to 4500.
.Statistical key figure 9101 (square meters) is used as the basis for the indirect activity allocation. This key figure is planned either as activity-type independent or activity-type dependent on the receiver cost center. The sender/receiver relationship is built up via indirect activity allocation, either activity-type independent or activity-dependent.
and
until the overview tree appears.If you are asked whether you wish to save the processed cycle, choose No.