Displaying a Cycle for Indirect Activity Allocation 

  1. Call up the transaction as follows:
  2. Menu Path

    Tools ® AcceleratedSAP ® Customizing ® Edit Project

    Transaction Code

    KSC8

  3. Choose SAP Reference IMG.
  4. Open the tree Controlling ® Cost Center Accounting ® Planning ® Allocations ® Activity Allocation ® Indirect Activity Allocation.
  5. Choose Define Indirect Activity Allocation.
  6. Place the cursor on the Change Plan Indirect Activity Allocation, choose Choose.
  7. If the Set Controlling Area dialog box appears, enter the following data then choose :

    Field

    Europe

    North America

    Controlling area

    1000

    2000

  8. Enter the following data:
  9. Field

    Europe

    North America

    Cycle

    I-IAP1

    I-IAP3

    Starting date

    01.01.1995

    01.01.1995

    This cycle is used only for company code 1000 Germany or 3000 U.S.A., as these are the only company codes in which indirect activity allocation occurs. Company codes 2000 Great Britain (or 4000 Canada) use assessment to allocate secondary costs.

  10. Choose .
  11. Choose .
  12. You see which areas are to be allocated using indirect activity allocation.

  13. To close the dialog box, choose .
  14. Choose First segment.
  15. Choose the Sender/Receiver tab page.
  16. You can see the specification of the sender and receiver cost centers for the allocation of cost center 1000 (Corporate Service). In this segment, the sender costs are allocated via activity type 1510 (caution, we use activity type categories 2 and 3).

  17. Double-click on the receiver Cost Center Group VC1-050 (VC3-050).
  18. The system displays the drilldown for the receiver cost center set. This contains all cost centers from numbers 1110 to 4500.

  19. Choose .
  20. Choose the Recvr tracing factor tab page.
  21. Statistical key figure 9101 (square meters) is used as the basis for the indirect activity allocation. This key figure is planned either as activity-type independent or activity-type dependent on the receiver cost center. The sender/receiver relationship is built up via indirect activity allocation, either activity-type independent or activity-dependent.

  22. Choose and until the overview tree appears.

If you are asked whether you wish to save the processed cycle, choose No.