Calling Up and Displaying the Split Planned Costs 

  1. Call up the transaction as follows:
  2. Menu Path

    Accounting ® Controlling ® Cost Center Accounting ® Planning ® Allocations ® Splitting

    Transaction Code

    KSS4

  3. Enter the following data:
  4. Field

    Europe

    North America

    Cost center

    Selected

    Selected

    Cost center

    4278

    4278

    Version

    0

    0

    Period

    01

    01

    To

    12

    12

    Fiscal year

    2000

    2000

    Background processing

    Deselected

    Deselected

    Test run

    Selected

    Selected

    Detail lists

    Selected

    Selected

  5. Choose .
  6. The Plan Cost Splitting: List screen, displays the distribution of the total planned costs for cost center 4278 to activity types 1420 and 1421.

  7. Select CTR 4278, then choose Cost elements.
  8. The system displays the distribution of all cost element numbers to the activity types. You can see how the values for cost element 449000 are distributed to activity type 1421 and cost element 459000 to activity type 1420.

  9. Choose .
  10. Select any row of cost element 449000, then choose Splitting Base.
  11. You can see that this cost element has been split according to splitting structure I1.

  12. Choose .
  13. Select the row of cost element 430000, then choose Splitting Base.
  14. No splitting structure was used here, so the distribution is based on the equivalence numbers of the activity types.

  15. Choose .
  16. Choose until the overview tree appears.

In the dialog box, choose Yes.