Material Requirements: Comparison of MRP List and Stock/Requirements List

Description

The MRP list displays the results of the last planning run. Changes that have occurred between planning runs are ignored in the MRP list.

Contrary to this logic, in the stock/requirements list, all current stock, receipt, and issue changes are displayed.

If you want to compare the MRP list with the stock/requirements list, you can do this using the compare functions. This means that you can compare the situation at the time of the last planning run with the current stock/requirement situation.

You can access the comparison from the following applications:

You then branch into the comparison of the 'Comparison of MRP List and Stock/Requirements List'.
In screen section 'Comparison', the systen displays the date on which the last planning run was carried out.
In the screen section, 'Period totals: MRP list' the system displays the planning result according to the period totals. The lines in which the data of the MRP list differ from the data in the stock/reqmts list are highlighted.
You branch into the compare screen, 'Current Stock/Requirements List'.
In the screen section, 'Comparison', the system displays the date on which the last planning run was carried out.
In the screen section, 'period totals', the system displays the stock/ requirements list according to period totals. The lines in which the data of the stock/requirements list differ from the data in the MRP list are highlighted.