Check Valuation Variants for CO Production Orders

In this step, you check the parameters for the valuation variants for CO production orders (production orders without quantity structure).

With the valuation variant you define the following:

Standard Settings

The SAP standard system contains predefined valuation variants. You can modify these valuation variants to suit your requirements by changing the standard strategy sequences. The default valuation variant for the preliminary costing of production orders without quantity structure is valuation variant "006 - Production Order - Planned".

Actions

1. Enter an alphanumeric key and a text for the new valuation variant.
2. Define the relevant valuation strategy
3. Assign the valuation variant to a costing variant.