In this menu option you define the location group and the move time matrix. In the move time matrix you can maintain the planned values for the move time within a location group as well as between two location groups.
For each entry you can maintain a minimum and a normal move time. In the case of a reduction scheduling is carried out with the minimum move time.
You can only calculate a move time using the move time matrix if both the source and the target work centers are assigned to a location group and the location groups are defined in the move time matrix.
So that the matrix does not become too large you should combine the work centers that are near one another in one location group.