Replenishment TO for the Production Plant 

Purpose

To create a replenishment transfer order for the production plant.

Prerequisites

The standard IDoc WMTOID01 must be used. The barcoded information must be generated in accordance with individual requirements, e.g. in the form of a Kanban chart.

Process Flow

Creation of a replenishment transfer order for the production plant is mapped as a storage function. The following scenario results if the system recognizes that a WM-managed production storage bin must be replenished:

  1. The material, quantity and storage bin are scanned in
  2. The data is sent and a TO is generated in the WM system.
  3. The TO is printed and physical transfer takes place to the storage bin.