Capacity Leveling 

  1. Call up the transaction as follows:
  2. Menu Path

    From the Capacity Planning node, choose Leveling ® Work Center View ® Planning Table (Graphical)

    Transaction Code

    CM21

  3. Enter the following data:
  4. Field

    Data

    Work center

    1320-01

    Plant

    1000

  5. Choose .
  6. The current orders whose operations result in capacity loads at the selected work center are displayed. By scrolling through the different charts in the planning table, you can analyze the information provided.

  7. For a better view, choose Settings ® Scale ® Monthly period split.
  8. To automatically dispatch one or several operations of an order, click the red rectangle in the order's diagram section to select the order and choose .
  9. The order disappears from the order pool and reserves a time segment in the work center section.

  10. To manually dispatch one or more operations of an order, select the order in the diagram section, drag it to the work center section with the mouse, and place it in a time period that you select.
  11. To deallocate an order, select it in the work center's diagram section and choose .
  12. The order is again displayed in the order pool.

  13. To analyze the changes made in scheduling, select an order in the order's diagram section and choose Order.
  14. Choose and write down the start and finish dates of the operation you selected.
  15. Choose until the Planning Table: SAPSFCG001 Finite Scheduling Forw./All Functs.Active screen appears.
  16. Drag the order to a valid section in the work center's diagram section. Make sure that you move the order to a valid and defined start and finish date.
  17. Select the order in the work center's diagram section and choose Order.
  18. Choose and compare the new start and finish date.
  19. Choose until the overview tree appears.
  20. Do NOT save.