Displaying the Capacity Load 

  1. Call up the transaction as follows:
  2. Menu Path

    From the Production node, choose Capacity Planning ® Evaluation ® Work Center View ® Load

    Transaction Code

    CM01

  3. Enter the following data:
  4. Field

    Data

    Work center

    1320-01

    Plant

    1000

  5. Choose .
  6. The available capacity and the capacity load is displayed split up according to weeks.

    You can also change the settings to a monthly period.

  7. To do so, choose Settings ® General.
  8. In the dialog box, enter the following data:
  9. Field

    Data

    Periods - month

    Select

  10. Choose .
  11. Select the month in which your orders must be processed and choose Cap. details/period.
  12. Your orders are displayed.

  13. Select an order (line) and choose Order header.
  14. Choose .
  15. The operations are displayed along with the corresponding times and the start and finish date that apply to your work center.

  16. Choose until you return to the Capacity Planning: Standard Overview screen.
  17. To change the period to be evaluated, choose Settings ® General.
  18. In the dialog box, enter the following data:
  19. Field

    Data

    Entry type

    A

    Start

    Any date in the future

    Int. finish

    Any date in the future

    Period - week

    Select

  20. Choose .
  21. The screen now appears with the new settings.

  22. To display the evaluation as a graphic, choose .