Use
In demand management, you enter the planned independent requirements for each of the next two months, 10,000 KG of material CH_5102 (primer coat black 500 L canister). You enter the requirements dates on a monthly basis.
Procedure
Menu Path |
Logistics ® Production - Process ® Production Planning ® Demand Management ® Planned Independent Requirements ® Create |
Transaction Code |
MD61 |
Make sure that Material has been selected.
Field |
Data |
Material |
CH_5102 |
Plant |
1100 |
Version |
00 |
Field |
Data |
Plant |
1100 |
Requirements type |
VSF |
Display – Period split |
Select |
Overview – Item screen |
Select |
Active |
Select |
History indicator |
Select |
To confirm the message, choose
.
The Create Planned Independent Requirements: Initial Screen appears.

If a requirement already exists, a warning message appears. Confirm all further screens until you can create another independent requirement.
Field |
Data |
P |
M |
Reqmts dt. |
In 2 months (in format MMJJ) |
Planned qty |
10000 |
P |
M |
Reqmts dt. |
In 3 months (in format MMJJ) |
Planned qty |
10000 |