Analyzing the Requirement Situation 

  1. Call up the transaction as follows:
  2. Menu Path

    From the MRP node, choose Evaluations ® Stock/Requirements List

    Transaction Code

    MD04

  3. Enter the following data:
  4. Field

    Data

    Material

    P-400

    Plant

    1000

  5. Choose .
  6. You see the planned orders (PlOrd.) that have been generated during MRP.

  7. Choose .
  8. Now switch to a component in the BOM. To do this, enter the following data:
  9. Field

    Data

    Material

    400-100

    Plant

    1000

  10. Choose .
  11. On the Stock/Requirements List as of ## Hrs screen, you see the planned orders (PlOrd.) generated by MRP as direct production (collective order).

  12. Choose .
  13. Remain on this screen.