Collective Orders 

Purpose

In this process, you create a collective order, schedule it, perform an availability check, and release the order. You then enter the confirmations, post the goods movements, and compare the planned and actual costs.

Prerequisites

If you need to create the necessary starting situation for this process, choose .

Process Flow

You can find the data for this process under .

  1. Analyzing the Requirement Situation
  2. Planning a Product
  3. Executing MRP
  4. Analyzing the Requirement Situation
  5. Converting the Planned Order into a Collective Order
  6. Scheduling the Collective Order
  7. Checking Availability for the Collective Order
  8. Releasing the Collective Order
  9. Confirming the Collective Order
  10. Material Withdrawals or Goods Receipt for the Production Order