Menu Path |
From the Production node, choose MRP ® Planning ® Single Item, Multi-Level |
Transaction Code |
MD02 |
Field |
Data |
Material |
P-400 |
Plant |
1000 |
Processing key |
NETCH |
Create purchase req. |
2 |
Delivery schedules |
3 |
Create MRP list |
1 |
Planning mode |
3 |
Scheduling |
1 |
Also plan unchanged components |
Select |
Display material list |
Select |
.To confirm the message, choose
.
The statistics overview appears.
You see the planning results based on the planned orders generated during MRP for the finished product.
In the dialog box, you can analyze the planned order.
On the overview, you can now investigate further materials or planned orders of the dependent requirements.
In the dialog box, choose Yes.